In his statement on the Monetary Policy, the RBI Governor highlighted that banks and NBFCs continue to exhibit financial stability, by way of strong liquidity positions, capital adequacy, and sustained profitability. NBFCs have shown improvement with better asset quality and declining GNPA ratios. Against this backdrop, the RBI today maintained a cautious yet forward-looking stance, keeping policy rates unchanged while focusing on strengthening financial stability, enhancing risk management, and reinforcing consumer protection through regulatory measures affecting banks and NBFCs.Some of the policy changes introduced by the RBI, which are expected to impact financial entities such as banks and NBFCs, are as follows:
Project loans, used to finance large infrastructure and industrial ventures like highways, power plants and railways etc., are fundamentally different from regular business or personal loans. Unlike typical loans that are repaid from either the borrower’s existing operations and balance sheet (in case of the former) or the borrower’s own credit worthiness (in case of the latter), project loans are forward-looking: they primarily rely on cash flows of the project, generated onlyafterthe project becomes operational. Because of this, delays in project completion due to various factors such as land acquisition issues and regulatory delays which may be beyond the control of the developer are common. These may arise from. Such delays, though being routine and not necessarily indicating borrower’s stress, triggered adverse asset classifications under the existing rules.
When the RBI introduced its 2019 prudential framework to enable early recognition and time bound resolution of stressed assets, it excluded such project loans from its scope (see para 25). As a result, these continued to be governed by old norms, specifically para 4.2.5 of the 2015 IRCAP and later, para 3 of Annex III under the RBI SBR Directions. However, these norms did not reflect the unique risks faced by project finance especially during the construction phase.
To address these issues, the RBI released the Draft Project Finance Directions in May 2024, proposing a dedicated regulatory framework tailored to project loans. The Project Finance Directions(‘Directions’) have been issued on 19 June, 2025. This article explores the need for such a framework, the changes brought in the regulatory regime, and their impact on borrowers and lenders.
Project finance vs other kinds of finance
In corporate lending, credit decisions are primarily based on the borrower’s balance sheet strength, existing cash flows and overall financial health. where the lender primarily assumes credit risk
In contrast, in project finance, repayments as well as the primary security depend primarily on the successful implementation and projected cash flows of a specific project, rather than the borrower’s overall financial position. Accordingly, the lender takes two different risks:
Project riski.e. the risk that the project may face commencement delays due to factors like regulatory bottlenecks, land acquisition issues or construction delays and;
Credit riski.e. the risk of inadequacy of cashflows to make the scheduled contractual payouts.
Importantly, in project finance, delays in cashflows often happen due to non-credit factors linked to project execution, mainly project delays. As a result, automatic downgrading of classification due to any project delay may not only fail to provide a true risk profile of the loan but also cause increased provisioning burden on the lender.
Overview of the Directions
The Directions deal with the following broad aspects:
Classification of projects and project finance;
Prudential requirements for extending project loans including:
Provisioning requirements;
Conditions for sanction, disbursement and monitoring.
Resolution and restructuring of project loans
Either due to stress;
Extension/ delays in DCCO.
Applicability
Classification of ‘project’ and ‘project finance’
Under the Directions, a project is defined as to involve capital expenditure for the creation, expansion or upgradation of tangible assets or facilities, with the expectation of long-term cash flow benefits [see para 9(l)], with the following features:
Project finance is a method of funding where the project’s cash flows/ revenue own revenues are the primary source of repayment as well as the and security for the loan [see para 9(m)].
It can be:
Greenfield (new project);
Brownfield (existing project enhancement).
To qualify as project finance under the Directions:
Note: Loan terms can differ across lenders if agreed by all parties
The earlier definition of project finance under the SBR Directions was generic and vague, referring merely to a “project loan” as any term loan extended for setting up an economic venture. The Directions have provided more clarity on what would be considered as project finance and have linked it to the definition of project finance under the Basel Framework, while also providing a quantitative threshold of 51%.
Project finance envisages the lender’s exposure in a project, which is typically in the process of being set up. The repayment will be from the project cashflow i.e. the payout structure is connected with the commencement of commercial operations of the project. The lending is based on the projected cash flows of the project rather than the balance sheet of the developer. It is distinct from asset finance, where loans are backed by existing assets generating income. Further, project finance differs from a working capital loan/general corporate purpose loan where the latter is towards financing the working capital needs of the developer entity based on the overall health of the entity.
Would it mean that project loans cannot have any other collateral and must solely rely on the project as the security? The answer is negative since the threshold specified allows to have other/ additional collateral, say, personal guarantee of the developer etc., however, the primary security shall be the project cashflows.
Other important terminology
DCCO
The Date of Commencement of Commercial Operations (DCCO) is a key milestone in project finance, marking the transition from construction to operational phase when a project begins to generate revenue.The Directions recognises three forms of DCCO. [see Para 9(e) to (m)]
CRE and its sub-category CRE-RH
Defined in Directions on Classification of Exposures as Commercial Real Estate Exposures, CRE refers to loans or exposures where repayment primarily depends on income generated by the real estate asset itself. This typically includes office spaces, malls, warehouses, hotels and multi-family housing complexes that are leased or sold in the open market. Since CRE is a sub-head of project finance, it also follows similar characteritics of project finance i.e.both repayment of the loan and recovery in case of default are closely tied to the cash flows from the real estate asset such as rental income or sale proceeds. [see para 9(b)]. The definition is aligned with the definiton of income-producing real estate (IPRE) under Basel norms. Our article discussing CRE can be assessed here. https://vinodkothari.com/2023/04/commercial-real-estate-lending-risks-and-regulatory-focus/
Commercial Real Estate – Residential Housing (CRE-RH) [see para 9(c)]
Since residential housing projects generally pose lesser risk and volatility compared to commercial properties, the RBI created a distinct sub-category within CRE called CRE-RH vide notification dated June 21, 2013. CRE-RH includes loans given to builders or developers for residential housing projects meant for sale.To classify as CRE-RH, the project must be predominantly residential and commercial components like shops or schools should not exceed 10% of the total built-up area (FSI). If the commercial area crosses this 10% threshold, the entire project will be CRE. This distinction isn’t just semantic, it has regulatory benefits. Since CRE-RH are subject to lower risk due to various reasons such as diversified cash flows and lower dependency on a single occpnt, RBI has assigned lower capital risk weights i.e. 75% to CRE-RH compared to standard CRE 100% and lower provisioning provisioning requirements (0.75% vs. 1%).
Prudential requirements
Provisioning requirements
In the context of project finance, where risks vary across different phases of a project’s lifecycle, a one-size-fits-all provisioning approach throughout the project life may not be relevant. .
Under the SBR, provisioning norms made no distinction between the construction and operational phases of a project. A uniform provisioning rate was applied i.e. 0.75% for CRE-RH and 1% for CRE while other loans were provisioned at 0.4% irrespective of whether the project was just starting construction or had already begun generating revenue. This approach, while simple, failed to reflect the heightened risks associated during the construction phase , such as delays, cost overruns, or regulatory hurdles.
To address this gap, the Draft Directions, proposed a conservative approach calling for a 5% provision during the construction phase and 2.5% during the operational phase, with the operational rate reducible to 1% if following conditions were met:
the project demonstrated positive net operating cash flows sufficient to service all current repayment obligations, and
there was a minimum 20% reduction in long-term debt from the level outstanding at the time of achieving DCCO.
These draft norms were considered overly harsh, particularly for long-gestation infrastructure projects where cash flows stabilise gradually.
Taking stakeholder feedback into account, the Directions adopted a more balanced g structure as follows:
Project type
Construction Phase
Operational phase – after commencement of repayment interest and principle
Commercial real estate (CRE)
1.25%
1%
CRE – Residential Housing
1%
0.75%
Other projects
1%
0.40%
DCCO deferred projects:
Additional provisioning to be maintained depending on the type of project:0.375% per quarter for infra projects0.5625% per quarter for non-infra projects
NPA project finance accounts
As per extant instructions
Provisionig for existing projects
Continued to be governed by extant norms;If resolution is done for any fresh credit event or change in terms occur after the effective date of these directions, then provisioning as per these Directions
Conditions of project finance
The onus is on the lender to ensure that the following conditions are met before extending any project finance. These conditions will ensure that the facility is structured prudently and is aligned with the implementation as well as cash flows of the project, thereby mitigating both credit as well as project risk. The requirements are more or less similar to the earlier Directions.
Repayment schedule during operational phase is designed to factor initial cash flows
Repayment tenor, including the moratorium period, if any, shall not exceed 85% of the economic life of a project.
This means there is a mandatory 15% tail period i.e. if the project has an economic life of 20 years and the loans are to be repaid in 17 years, the last 3 years are the tail period.Tail period gives comfort to the lender that in case of any default or delay in repayment by the time of maturity, there is still some period left to recover dues from the project cash flows after the scheduled loan maturity.
Would this mean that a borrower cannot obtain a top-up loan after the expiry of 85% of the loan tenure?
The requirement applies to loans with all kinds of tenures, either short or long.
One borrower, multiple lenders
If a project is financed by more than one lender, RBI mandates that the DCCO, whether original, extended or actual, shall be the same across all lenders. This will ensure that:
DCCO is uniform across all lenders
Project progress as well as any delays are uniform across all lenders
Uniform asset classification, preventing any lender from having a different provisioning status.
To ensure balanced risk sharing, the Directions have put consortium lending limits (Para 15): Where projects are under-construction:
Aggregate exposure of all lenders is ≤ ₹1,500 crore: each lender shall hold at least 10% of total exposure;
For projects with exposure > ₹1,500 crore: each lender must hold at least 5% or ₹150 crore, whichever is higher.
These caps essentially require participating lenders to hold sufficient skin in the game and thereby promote responsible credit appraisal as well as avoid risk from being concentrated in a few lenders, especially where other lenders have negligible exposure and hence, less incentive to ensure monitoring.
Inter-lender transfer
These minimum exposure norms will not apply to operational phase projects;
In design or construction phase, lenders are permitted buy/sell exposure only under syndication arrangements as per TLE, and within the exposure limits
In operational phase, exposures can be freely transferred as per TLE norms.
This may be because construction and pre-operational stages are inherently more uncertain and riskier, and therefore, the regulator requires lenders who are willing to remain committed and not exit easily to avoid creating instability.
Project lifecycle – 3 different phases
A project has been divided into 3 phased viz Design, Construction and Operational.
Why does this classification matter?
The regulatory framework treats each phase differently for various risk, compliance and prudential reasons.
Disbursement discipline (Para 21)
Disbursal of funds must be linked to project completion milestones i.e. completion of phases.
Lenders must also track progress in equity infusion and other financing sources as agreed at financial closure
Asset classification (Para 22 & 29)
In design and construction phases, loans can be classified as NPA based on recovery performance, as per IRACP norms.
Once an account is classified as NPA, it can only be upgraded after demonstrating satisfactory performance during the operational phase
Resolution trigger (Para 23)
If any credit event (e.g., default) occurs with any lender during the construction phase, a collective resolution process is triggered
Provisioning norms (Para 32)
Provisioning rates are higher for projects under construction
Once the project enters the operational phase, provisioning reduces, reflecting lower credit risk.
Mandatory requirements before sanctioning a project finance loan: (13)
Achievement of financial closure and documentation of original DCCO;
Project specific disbursement schedule vis a vis stage of completion is included in loan agreement
Post DCCO repayment schedule designed to factor initial cash flows
Prudential conditions related to disbursement and monitoring:
Lender to ensure the following:
Clearances are obtained by the lender:
All requisite approvals/clearances for implementing/constructing the project are obtained before financial closure.(examples: environmental clearance, legal clearance, regulatory clearances, etc.)
Approvals/clearances contingent upon achievement of certain milestones would be deemed to be applicable when such milestones are achieved.
Availability of sufficient (prescribed) minimum land/right of way with the lender before disbursal of funds
This would mean that lender must ensure that the builder executing the project has either:
Ownership of the land (through purchase, lease etc.) or
Legal rights to use/access the land i.e. Right of Way.
For PPP projects, disbursal of funds to occur only after declaration of the appointed date.
Except where non-fund based facilities are mandated by the concessioning authority as a pre-requisite for declaration of the appointed date itself;
Disbursal to be proportionate
To stages of completion of project, infusion of equity or other sources of finance and receipt of clearances
Lender’s Independent Engineer/Architect to certify the stages
Creation and maintenance of a project finance database (see para 37):
Every lender to capture and maintain, on an ongoing basis, project specific information relating to:
Debtor and project profile;
Change in DCCO;
Credit events other than deferment of DCCO;
Specifications of project
Any updation shall be made within 15 days from any change in information;
Necessary systems to be placed within 3 months from the effective date ie by 1st January, 2026
Resolution of Project Loans
Prudential norms for resolution
Lender to monitor performance of project on on-going basis;
Expected to initiate a resolution plan well in advance.
Collective resolution to be initiated by the lenders in case credit event happens with any one lender
In case of any credit event;
Lender to report the same:
to the Central Repository of Information on Large Credit and;
to all other lenders, in case of consortium lending.
Lender to take a review of debtor account within 30 days.
Inter creditor agreement and decision to implement a resolution plan may be done during this period.
Implement the resolution plan within 180 days from the end of the review period.
Resolution plans involving extension of DCCO
Paragraphs 26 to 28 provide a structured framework under which project loans may continue to be classified as ‘standard’ despite delays in project completion, provided specific conditions are met. The objective is to offer flexibility to lenders and borrowers in addressing genuine project delays or cost escalations, without triggering an immediate downgrade to NPA so long as the resolution is timely and prudently implemented.
Permitted DCCO deferment
The DCCO may be deferred, with a corresponding adjustment in the repayment schedule. However, such deferment is subject to the following maximum limits:
Up to 3 years for infrastructure projects
Up to 2 years for non-infrastructure projects (including commercial real estate)
Cost overrun associated with the DCCO deferment:
A cap of 10% of the original project cost, over and above Interest During Construction (IDC)
The overrun must be financed through a Standby Credit Facility sanctioned at the time of financial closure
Post-funding, key financial metrics such as the Debt-Equity ratio and credit rating must remain unchanged or show improvement in favour of the lender
Deferment in DCCO associated with change in scope and size
Rise in project cost (excluding cost overrun) is at least 25% or more of the original project outlay
Reassessment of project viability by the lender before approving the revised scope and DCCO
If the project has an existing credit rating, the new rating must not deteriorate by more than one notch; if unrated and aggregate lender exposure is ₹100 crore or more, the revised project must obtain an investment-grade rating
This benefit of maintaining ‘Standard’ classification due to a change in scope can be availed only once during the project’s life
Resolution plan (‘RP’) deemed successfully implemented only if:
Necessary documentation completed within 180 days from the end of the Review Period and;
Revised capital structure and financing terms are duly reflected in the books of both the lender and the borrower.
Immediate downgrading to NPA if the resolution plan is not implemented within the timeline and conditions above
Once NPA, account can be upgraded only after:
Satisfactory performance post actual DCCO, in case of non-compliance with conditions of resolution plan;
Successful implementation of resolution plan, in case of non-implementation of RP within the specified time.
https://vinodkothari.com/wp-content/uploads/2023/06/vinod-kothari-logo.png00Staffhttps://vinodkothari.com/wp-content/uploads/2023/06/vinod-kothari-logo.pngStaff2025-06-23 16:44:502025-06-26 14:54:33Balancing flexibility and discipline: Analysis of RBI’s Project Finance Directions, 2025